A series of closures will be in place while the M6 J16 roundabout, the slip roads are resurfaced.
The closures are applied in 3 phases and will take place from 8pm – 6am.
Phase 1: the north roundabout closures started Monday 23 February and will finish Friday 27 February
- northbound on slip closed
- southbound off slip closed
- A500 Eastbound closed
- occasional closures to the B5078.
Phase 2: south roundabout – Monday 2 March to Friday 11 March
- northbound off slip closed
- southbound on slip closed
- southbound off slip closed
- A500 Westbound closed
- occasional closures to the B5078
Phase 3: A500 – Thursday 12 March to Friday 27 March
- A500 total closure
- southbound off slip closed
- occasional closures to the B5078.
Kevin Harvey, Project Sponsor, Highways Agency said:
The junction suffers heavy congestion during morning and evening peak times.
The improvements to the junction involve installing traffic signals, widening of the roundabout and the northbound and southbound exit slip roads and an upgrade to the A500 corridor.
As always we’ve planned the work very carefully to create as little disruption as possible.
Due to the nature of the work the scheduled road closures can be subject to change at short notice. For more information about this scheme and details of traffic management throughout the project please go to the dedicated project pages.