Posted: Wed 30th Oct 2024

Menai Bridge reopens for winter after hanger replacement

News and Info from Deeside, Flintshire, North Wales
This article is old - Published: Wednesday, Oct 30th, 2024

The Menai Suspension Bridge will reopen to traffic on Saturday, 2 November, following the completion of essential repairs.

Crews have successfully replaced all 168 of the bridge’s hangers, marking the end of phase one in the long-term restoration project.

The reopening will temporarily lift the bridge’s 7.5-tonne weight restriction, providing local residents, businesses, and visitors with full access over the winter period.

The decision to delay the start of phase two works until March allows the bridge to remain fully operational throughout the busy winter months.

Transport and North Wales Cabinet Secretary Ken Skates noted the importance of minimising disruption for residents and the local economy during this time.

“The completion of phase one works is great news,” said Skates. “It has been a challenging time, and I want to place on record my thanks to everyone affected by the works.”

The reopening will bring a number of benefits, including a smoother and more efficient phase two restoration, aided by better weather conditions anticipated in spring.

The bridge will provide an alternative route across the Menai Strait should the Britannia Bridge (A55) face disruptions from severe weather, incidents, or emergencies. Additionally, the temporary lift of the 7.5-tonne weight limit will enable heavy goods vehicles and other larger vehicles to cross safely.

Local businesses are expected to benefit from increased accessibility, particularly during the Christmas period, and Holyhead Port will remain operational for longer. Additionally, the bridge’s reopening allows the ‘Always Aim High’ Anglesey Half Marathon to incorporate it into their route, creating new business opportunities and drawing visitors to the community.

The Cabinet Secretary for Transport and North Wales, Ken Skates, said:

“We’ve listened to the feedback from local communities and have decided to pause the start of phase two works to allow for the full reopening of the bridge over the winter period.”

“But rest assured this delay will not affect the 200th anniversary of the bridge in January 2026.”

Before the start of phase two works, a period of communication will take place with the general public and stakeholders.

Check live fuel prices near you before you set off.

Spotted something? Got a story? Email news (@) deeside.com


Latest News

LATEST NEWS...

Why a Heat Press and Heat Transfer Vinyl Are Still Essential Tools for Creative Businesses Using HTVRONT

News

Mold Carnival returns to Maes Bodlonfa Fields on Sunday 5 July with free entry

News

Chester Haematology Centre to open at Countess of Chester Hospital in late July

News

Young footballers in Flintshire could land brand new kit thanks to Euro tournament giveaway

News

Jade Jones Pavilion launches free monthly coffee morning open to all in Flint

News

Welsh skills rising among Flintshire council staff as annual language report published

News

Welsh Government announces £145 million for NHS Wales to cut waiting times

News

Chester Zoo welcomes rare male giraffe to join conservation breeding programme

News

Public meeting called on future of Greenfield Valley fishing pool

News