A494t A494 Pinfold Lane To Alltami Lgts, Alltami, Flintshire |
24 March — 26 March |
Delays likely Traffic control (Stop/Go boards) |
Works location: Outside Elm Farm |
Works description: Overhead Line Work. Outage 25/03/14 |
Responsibility for works: Scottish Power |
Current status: Planned work about to start |
|
|
A5119 Northop Road, Flint, Flintshire |
24 March — 01 April |
Delays likely Traffic control (two-way signals) |
Works location: Outside 114 To 116 , Northop Road |
Works description: Install 18m Of 1 Way Poly Duct In Footway,Provide 1 Provide/Recover 1 Nga Cab And Base (1.5m X 0.5m) |
Responsibility for works: BT |
Current status: Planned work about to start |
|
|
A548 Chester Road, Flint, Flintshire |
24 March — 01 April |
Delays likely Traffic control (two-way signals) |
Works location: (Pcp7) Outside 235 Along Footway To Opposite Junction Albert Avenue On Chester Road, |
Works description: Install 27m Of 1 Way Poly Duct In Footway,Provide 1 Provide/Recover 1 Nga Cab And Base (1.5m X 0.5m) |
Responsibility for works: BT |
Current status: Planned work about to start |
|
|
B5441 Station Road, Queensferry, Flintshire |
24 March — 25 March |
Delays likely Traffic control (two-way signals) |
Works location: In The Area Of The Bridge- |
Works description: 2 Mid Week Day Time Half Road Closures With 2 Way Lights And Footpath Closure Required For Fixing Guttering And Downspouts. 24/03/2014 7:00 Am 24/03/2014 4:00 Pm 25/03/2014 7:00 Am 25/03/2014 4:00 Pm |
Responsibility for works: Network Rail Infrastructure Ltd |
Current status: Advanced planning |
|
|
Seahill Road, Saughall, Chester, Cheshire West And Chester |
24 March — 31 March |
Delays likely Traffic control (two-way signals) |
Works location: Road Crossing – Main Located In The Opposite Footpath Across Fromplotr/O Sunny Bank, Seahill Road |
Works description: Lay 31m New Service Of Which 6m Will Be In Public To Main In Footway |
Responsibility for works: National Grid Gas Plc |
Current status: Advanced planning |
|
|
Raymond Street, Chester, Cheshire West And Chester |
24 March — 04 April |
Delays likely Traffic control (multi-way signals) |
Works location: Junction Of Raymond Street And Access Road To Tower Wharf In Carriageway And Footway |
Works description: Install New Bulk Meter – Traffic Management In Accordance With Chapter Eight Including Maintaining A Safe Passage For Pedestrian Access. |
Responsibility for works: Dee Valley Water Plc |
Current status: Advanced planning |
|
|
A5119 Main Road, Soughton, Flintshire |
24 March — 25 March |
Delays possible Traffic control (two-way signals) |
Works location: From Corwenfa To 50 Metres North |
Works description: Extend Overhead Line Pole And Install A New Service |
Responsibility for works: Scottish Power |
Current status: Planned work about to start |
|
|
|
|
Saughall Road, Chester, Cheshire West And Chester |
25 March — 27 March |
Delays possible Traffic control (give & take) |
Works location: Blacon: Col: 71: Opposite House 202 |
Works description: Replace Concrete Column With 8mtr Tubular Column And 100w Arc Lantern Blacon |
Responsibility for works: Cheshire West And Chester Council |
Current status: Advanced planning |
|
|
Saughall Road, Chester, Cheshire West And Chester |
25 March — 27 March |
Delays possible Traffic control (give & take) |
Works location: Blacon: Col: 74: At / Outside House 234 |
Works description: Replace Concrete Column With 8mtr Tubular Column And 100w Arc Lantern Blacon |
Responsibility for works: Cheshire West And Chester Council |
Current status: Advanced planning |
|
|
Saughall Road, Chester, Cheshire West And Chester |
25 March — 27 March |
Delays possible Traffic control (give & take) |
Works location: Blacon: Col: 85: At / Outside House 296 |
Works description: Replace Concrete Column With 8mtr Tubular Column And 100w Arc Lantern Blacon |
Responsibility for works: Cheshire West And Chester Council |
Current status: Advanced planning |
|
|
Saughall Road, Chester, Cheshire West And Chester |
25 March — 27 March |
Delays possible Traffic control (give & take) |
Works location: Blacon: Col: 84: At / Outside House 290 |
Works description: Replace Concrete Column With 8mtr Tubular Column And 100w Arc Lantern Blacon |
Responsibility for works: Cheshire West And Chester Council |
Current status: Advanced planning |
|
|
Saughall Road, Chester, Cheshire West And Chester |
25 March — 27 March |
Delays possible Traffic control (give & take) |
Works location: Blacon: Col: 75: Opposite Stamford Road |
Works description: Replace Concrete Column With 8mtr Tubular Column And 100w Arc Lantern Blacon |
Responsibility for works: Cheshire West And Chester Council |
Current status: Advanced planning |
|
|
Eaton Road, Eccleston, Chester, Cheshire West And Chester |
25 March — 07 April |
Delays possible |
Works location: Sign Outside Old Rectory Cottage Eccleston |
Works description: ‘New Electrical Service To Street Furniture’ ‘The Excavation And Reinstatement Of The Footway For The Connection Of Electrical Supply To Street Furniture.’ |
Responsibility for works: Cheshire West And Chester Council |
Current status: Advanced planning |
|
|
Dolfechlas Road, Rhydymwyn, Flintshire |
25 March — 26 March |
Delays possible Traffic control (Stop/Go boards) |
Works location: From Pinewood Heights To The Paddock |
Works description: Underground Existover Overhead Service, Overhead Line Works, Transfer Overhead Line Service, Extend Overhead Line Pole And Replace Overhead Line Pole And Stay |
Responsibility for works: Scottish Power |
Current status: Planned work about to start |
|
|
King Street, Leeswood, Flintshire |
24 March — 02 April |
Delays possible Traffic control (two-way signals) |
Works location: Outside 7 Bryn Clyd |
Works description: Excavate To Locate & Repair Low Voltage Fault. Excavate Approximately 4 X Joint Bays & 8 Metre Trench In Footway |
Responsibility for works: Scottish Power |
Current status: Planned work about to start |
|
|
Kingsway, Chester, Cheshire West And Chester |
24 March — 26 March |
Delays possible Traffic control (give & take) |
Works location: Works Outside Number 153 In Flagged Footway |
Works description: Install Meter At Boundary (Traffic Management In Accordance With Chapter Eight Including Maintaining A Safe Passage For Pedestrian Access) |
Responsibility for works: Dee Valley Water Plc |
Current status: Advanced planning |
|
|
Llys Alun, Rhydymwyn, Flintshire |
25 March — 26 March |
Delays possible |
Works location: From Property 54 To The Junction Of Vicarage Road |
Works description: Overhead Line Works Only – No Excavation |
Responsibility for works: Scottish Power |
Current status: Planned work about to start |
|
|
Old Wrexham Road, Chester, Cheshire West And Chester |
25 March — 27 March |
Delays possible Traffic control (give & take) |
Works location: 4 Old Wrexham Road, Chester, Cheshire West & Chester |
Works description: Sewer Repair |
Responsibility for works: Welsh Water |
Current status: Advanced planning |
|